The Highways England Proposals

Overview

  • Project: Lower Thames Crossing (LTC)

    • A new road linking Kent and Essex via a tunnel under the Thames.

    • Promoted as a solution to congestion at the Dartford Crossing.


Location & Route in Kent

  • Starting Point: New junction on the A2 near Gravesend.

  • Ending Point: M25 between junctions 29 and 30, on the north side of the Thames.

  • Key Features:

    • A 1.8-mile twin-bore tunnel.

    • A new junction on the A2 east of Gravesend.


Kent-side Route & Land Affected

  • Tunnel Portal Location: South of the A226 near Chalk, east of Gravesend.

  • Route (from the Thames north to south):

    • The road will pass through the former Southern Valley Golf Course (permanently closed) and open farmland.

    • It will cross Thong Lane, impacting homes at the south east corner of Riverview Park.

    • The road will curve towards the A2, passing near Thong village, and merge into the redesigned A2/M2 corridor.


A2 Junction at Cobham

  • New Junction: The new LTC junction will be added to the A2.

  • Lane Reductions: The A2/M2 will be reduced from four lanes to two between the LTC junction and the M2/A289 junction at Three Crutches.


Massive, Overbuilt Interchange

  • Design: A large, multi-layered concrete structure with flyovers, slip roads, and ramps connecting the LTC to the A2.

  • Land Use: Significant land will be taken, requiring earthworks and creating new embankments and cuttings.

Environmental Impact

  • Land Affected:

    • Destruction of parts of the Kent Downs Area of Outstanding Natural Beauty (AONB).

    • Disruption of wildlife corridors connecting the Thames Estuary with inland reserves.

  • Impact: Increased air and noise pollution from higher traffic volumes in Gravesend, Shorne, Cobham, and surrounding areas.


Construction & Timeline

  • Duration: The construction is expected to take at least six years, though delays are likely.

  • Impacts:

    • Compulsory land acquisition for homes, businesses, and farmland.

    • Roadworks and diversions will cause extended disruptions on the A2, A226, and other local roads.


Tunnel Tolling

  • Toll System: The LTC will implement a new toll system based on dynamic differential charging.

  • Pricing: National Highways plans to adjust pricing to encourage drivers to use the LTC over the Dartford Crossing.